Install sleepers and backfill.
How to build a concrete sleeper retaining wall with steel posts.
The ridgi system comprises reinforced concrete sleepers and strong long lasting 60uc hot dipped galvanised steel posts and fence brackets.
Tie a string around one post then tie the other end of the string to the other post.
Step 4 installing sleepers backfilling the next day you can slide your sleepers into your posts.
Retaining wall system that has been designed engineered and certified specifically for retaining walls garden beds and edging up to a height of 900mm.
For example if your wall is going to be 800mm high the holes for your posts should be 500mm deep.
The traditional way of building a sleeper wall is horizontal.
The benefits of using a durawall concrete sleeper retaining wall are numerous.
This will help you in aligning your steel posts.
This means you won t have to worry about termites.
Time now to concrete your posts into position.
Durable it will last at least 4 times longer than a timber wall.
You may need to pack one side at the bottom to get you level perfect at the top.
Before moving onto the next post place into position the intervening bottom sleeper.
Building a retaining wall with concrete sleepers is one of the easiest methods you can use to build a retaining wall.
Using sleepers as your posts costs about a third of the price of h beams.
Make sure the line formed by the string is a straight line.
Use landscaping screws to fix these two rows together and then continue this until you have the height of wall you want.
Starting at one end of the wall insert the appropriate post and concrete into position ensuring that it is at the required height and vertically level.
Drive two wooden posts on the ground one on each side of your wall.
Reinforced concrete sleepers and galvanised steel posts step 1.
Sleeper retaining wall posts come in two varieties steel galvanised h beams or a vertical sleepers.
Preparing the area clear and level your site where you plan to build the retaining wall.
That will allow the next post to be better positioned.
Maintenance free concrete sleepers will not rot burn warp split or flake and is resistant to termites white ants.
Please ensure you leave 200mm behind the retaining wall area for backfill.
Lay out the first row of sleepers horizontally and then the next layer on top like bricks.
Dig the holes for the posts.
Other systems you can use include timber sleepers which are also very light and easy to install but are also prone to rotting fading and white ant damage.
Continue with the other post and keep a minimum 40mm for lean back.
Concrete the posts after confirming they are at an equal level.
Alignment place a star piquet or peg at both ends of the proposed wall.